CE Board MSTE Problem 6 (Nov 2021): Calculate Hourly Sand & Gravel Production of a 2.68 m³ Wheel Loader 🚜
Learn how to estimate the hourly loose volume (LCM) production of a 2.68 m³ wheel loader excavating sand and gravel from a pit, based on engineering mathematics principles.
Sol Usman Jr
64 views • Mar 14, 2024
About this video
CE NOV 2021 - Estimate the hourly production in loose volume (LCM) of a 2.68 m^3 wheel loader, excavating sand and gravel (average material) from a pit and moving it to a stockpile. The average haul distance is 61 m .Effective Grade is 6%, bucket fill factor is 1.0 , and Job efficiency is 50 min/hr<br />Basic Time Cycle = 0.50 min<br />Travel Time = 0.30 min<br />-<br />paki pindot po sa "LIKE" button mga Engr.<br />and click SUBSCRIBE na rin po if hindi pa po kayo naka "SUBSCRIBE"<br /><br />Maraming salamat po sa inyo mga Engineers and Future Engineers.<br />mabuhay po kayong lahat.<br />-<br />FB Page - https://www.facebook.com/MrComputerCiviLEngineer<br />Tiktok - https://www.tiktok.com/@SolUsmanJr<br />-------------<br />CREDIT:<br />-------------<br />Soundtrack:<br />Ace Attorney Dual Destinies - Apollo Justice (I'm fine)<br />Ace Attorney Spirit of Justice (Credit Theme)<br /><br />Avatar:<br />SuperME Cartoon Avatar Maker (mobile app)<br /><br />Reference:<br />"Licensure Exams for Civil Engineering" by BESAVILLA<br />"CE Reference for Licensure Examination" by GILLESANIA<br />-<br />#SolUsmanJr<br />#ceboardexam <br />#civilengineeringlicensureexam
Video Information
Views
64
Duration
2:22
Published
Mar 14, 2024
Related Trending Topics
LIVE TRENDSRelated trending topics. Click any trend to explore more videos.